The morning today was spent preparing all of the main support beams for the 2nd floor floor. There is a large steel beam going across the kitchen and great room to support the 2nd floor exterior brick wall which does not stick out as much as the first floor. Then there are the reinforced, engineered wood beams that need to be assembled and craned in to place for the other section of the floor.
No comments:
Post a Comment