Friday, July 8, 2016

Scaffolding set up

BHM Exteriors was in all day setting up the front wall scaffolding.  Done improperly, this takes 2-3 hours.  Done according to Ministry of Labour and safety guidelines - this takes 4 guys a full day.  Safety first!




Thursday, July 7, 2016

Front door?

The front door was installed today... just kidding - obviously this is a temporary door to keep nosy neighbours out of the house :-).


Wednesday, July 6, 2016

HVAC Starts

Pinewood was in today to start their rough-in of the heating, ventilation and air conditioning (HVAC).  First up is to cut all of the vents and holes for the upstairs ductwork.  As usual, I had to go over with the crew exactly how to avoid running ducts where we didn't want them, and what areas we were comfortable with "furring out" or cofferring.


Tuesday, July 5, 2016

Plumbing Starts

The plumbing rough-in work began today.  Tony made good progress, leaving about two days of work to complete the drains and then he starts the water lines.




Monday, July 4, 2016

Basement Framed

Miguel's guys were in today framing the basement - nice to finally see some walls down here.  Now the HVAC and plumbing can proceed from top to bottom.



Basement Framed

Miguel's guys were in today framing the basement - nice to finally see some walls down here.  Now the HVAC and plumbing can proceed from top to bottom.



Friday, July 1, 2016

Marking up

The cleaning crew was in today, getting the place reasonably clean - enough for me to mark the house up with kitchen, bathroom and bed locations.  This is always helpful for both the owners and the trades.  Rough-ins start next week, and HVAC, plumbing and electrical all have to know where things are in order to do their job correctly.