Monday, August 22, 2016

Clock Ticking

I always like to have a cooling off period between the rough-ins (electrical, HVAC, plumbing) and the insulation phase.  It's never a nice thing to go back and start making holes in drywall to install something that was missed, so this week long period is a good chance to catch our breaths.

That said, the cool off period has been extended four more days, as the stair company we're using, Stairtech Industries, has experienced manufacturing delays.  I've been assured they are back on track, and we should have the stairs installed on Thursday.

We are still looking at options on the exterior of the house.  Once that's done and the drywall, trim and doors have been delivered, we can pretty much complete the outside of the house.