Saturday, July 30, 2016

Rough-in carpentry... we have a roof!

The rough-in phase of carpentry is usually pretty fun... it's the last phase of carpentry that really drives the final look of the house.  For example, we now have a front roof above the porch, which as really altered the look, positively, of the front of the house.



The guys worked from top to bottom, making it down to the main floor by end of day.  


In the garage, the boxes were added to give enough insulation around the ducts to keep the air warm/cool for the upper bedroom.


Friday, July 29, 2016

Electrical Service Set to Go

Kevin completed the meter box and service pole, so we are ready for inspection (which should happen next Tuesday or Wednesday).



The mason's continued on to the East side of the house.

Thursday, July 28, 2016

Back complete

The guys finished the back of the house - I really like the look of the backyard.  Marlen and Danny and the kids will have many fun years enjoying their beautiful back yard (once we get some sod back there!).

It was another busy day inside the house, but more on that in a later post.



Wednesday, July 27, 2016

I can see the back yard!

We managed to fill a 40 yard bin by 5pm today with 45 yards of garbage!  The driver from Arizon was nice enough not to swear too much with the size and height of the load.  It is very nice to see the backyard, and you can also see the progress they've made on the brick.

Unfortunately, we've run out of brick (credit cards tend to get maxed during the build process!), but we'll be getting more tomorrow and they can finish the top and move to the last side after that.


Besides the heavy concentration of clean up, Kevin was doing his last bit of work before calling for inspection.  We should have power soon!

Tuesday, July 26, 2016

It was another busy one...

Masons, electrician, plumber, HVAC, rough-in framers and the cleaning crew has finally arrived - it was another busy day at 48 Edgecroft.  

Karol works on the back wall...


Rui drills the sump drain hole...


Andy hangs ductwork...


Mario runs water pipes...


Louis changes the bathroom door location and size...


Kevin runs the kitchen 20amp wiring...


And pedro finishes the coffered ceiling in the master bedroom!


No pics of the cleanup...it's just not that glamorous, but very rewarding!

Monday, July 25, 2016

HVAC, Plumbing and brick!

We continue to hum along on this project - the masons have move the scaffold to the back and were loading up bricks on the scaffold all day.


Meanwhile, work is progressing on the basement, with both HVAC and plumbing working in harmony.  We are aiming to drywall in 3 weeks.

Saturday, July 23, 2016

Moving on

Although I don't have a pic... I will wait until the scaffolding is down, the boys just finished the West side - ahead of schedule and looking great.  We will spend the early part of next week cleaning the wall and moving the scaffold, then it's on to the back.  At this rate, we should be done brick in less than 10 days.

Friday, July 22, 2016

Plumbing passed, brick moving along

The City was in today for the scheduled plumbing rough in.  This involves checking that the water lines can handle 100 psi of compressed air without a leak for an extended time (we've had the loaded for a week, so we're good to go!) as well as filling up the drains and vents to the roof to show that they are also water tight.  Then, we go through each plumbing zone, making sure that everything is to code, properly vented and that the ABS pipes are not going through framing they shouldn't.  Of course, with some plumbers, an inspection can be very stressful.... but not with Tony.  Passed!


Meanwhile, BHM is cooking along - in both ways.  The weather has been incredible, though quite hot on the sunny side of the house.  They have finished the 2nd third of the side, and are looking to finish the top of the wall tomorrow.  I have to say, the neighbour on this side of the house is one of the nicest guys I've worked next to!



Thursday, July 21, 2016

Front brick

While the guys have started the West side, this is the first time we can see the entire front side.  Though the final product will look much different when the porch roof and other details are added, I'm really liking it so far.


Pinewood was also in today, getting close to finishing the basement rough in.

Wednesday, July 20, 2016

Brick moves West

More electrical inside, while Tom has started the West side of the house.  He's promising three days of brick there... let's count!  1.....




Tuesday, July 19, 2016

Pot lights

After a detailed walk-through with "the boss" (Marlen.... sorry Danny!), Kevin was ready for the installation of all of the pot lights on the top two floors.  His progress has been fantastic.


Meanwhile, Tom ended up finishing the brick on the front in the late of the day.

Monday, July 18, 2016

Front brick work

While Kevin continued the electrical rough-in inside, Tom and his team worked their way up the front of the house with the brick.  If all goes well, they'll finish tomorrow and continue along the West side.


Friday, July 15, 2016

Plumbing, electrical, stone... continues!

A lot more progress today.  Tony was in finishing the water connections, Kevin and his crew were in getting everything down to the basement, and Tom was in working on the Southeast corner so we can install the angle iron above the garage and finish the stone sections of the house by tomorrow.  



Thursday, July 14, 2016

Work progresses...

Despite rain and a reduced team, Thom managed to get a half day of work done on the stone in the front.  It looks great, though you can't see much through the scaffolding!  Meanwhile, the Pinewood guys got most of the big things hung in the basement and Kevin made it down to the first floor already.  Good progress team!


Wednesday, July 13, 2016

Another crazy day...

4 trades... 14 people... no fights!  Wow.  We had the window guys deliver and install today, the mason's continue outside on the front, electrical start on the top floor and the HVAC guys working in the basement.  On a hot day like today (close to 40 degrees), we managed to get a ton of work completed in perfect harmony - I love days like this.







Tuesday, July 12, 2016

Stone and plumbing

Thom started the stone work at the front today - sweet!  We're doing a combination of 70% owen sound and 30% tiger stripe, a nice mix that will only look better over time.


Meanwhile, Tony was busy with installing the water lines throughout the house.  It was one of those hot days where working in the basement took longer than working upstairs...lol.


Good progress - by mid-day, we had the entire southwest corner of the house done.  Now we continue along the front and if the window guys show up as promised tomorrow, we'll have a different looking house by end of week!


Monday, July 11, 2016

Stone arrives

While we wait for the custom HVAC fittings for the basement takeoff, preparations are underway for the front of the house.  The stone, steel lintels and limestone sills arrived today.  We should be starting installation Wednesday.


Friday, July 8, 2016

Scaffolding set up

BHM Exteriors was in all day setting up the front wall scaffolding.  Done improperly, this takes 2-3 hours.  Done according to Ministry of Labour and safety guidelines - this takes 4 guys a full day.  Safety first!




Thursday, July 7, 2016

Front door?

The front door was installed today... just kidding - obviously this is a temporary door to keep nosy neighbours out of the house :-).


Wednesday, July 6, 2016

HVAC Starts

Pinewood was in today to start their rough-in of the heating, ventilation and air conditioning (HVAC).  First up is to cut all of the vents and holes for the upstairs ductwork.  As usual, I had to go over with the crew exactly how to avoid running ducts where we didn't want them, and what areas we were comfortable with "furring out" or cofferring.


Tuesday, July 5, 2016

Plumbing Starts

The plumbing rough-in work began today.  Tony made good progress, leaving about two days of work to complete the drains and then he starts the water lines.




Monday, July 4, 2016

Basement Framed

Miguel's guys were in today framing the basement - nice to finally see some walls down here.  Now the HVAC and plumbing can proceed from top to bottom.



Basement Framed

Miguel's guys were in today framing the basement - nice to finally see some walls down here.  Now the HVAC and plumbing can proceed from top to bottom.



Friday, July 1, 2016

Marking up

The cleaning crew was in today, getting the place reasonably clean - enough for me to mark the house up with kitchen, bathroom and bed locations.  This is always helpful for both the owners and the trades.  Rough-ins start next week, and HVAC, plumbing and electrical all have to know where things are in order to do their job correctly.