Friday, May 13, 2016

Excavation and Shoring

Today we finished the excavation and got that concrete under the walkout footings poured.  We have quite the water issues on the property, and with a weekend of rain in the forecast, we've got a high powered pump on site to hopefully keep things dry.




By the middle of the day, it was clear we would need some good shoring to protect the side wall excavations.  With quick team work between Juvee, Downtown Lumber and George, we had 8 foot sections of angle irons driven in to support 3/4" plywood shores. 